TDR rate · Hyderabad
58% – 65%
of government market value
- Issuing authorities
- GHMC · HMDA
- Governing rule
- G.O. Ms. No. 95 and G.O. Ms. No. 16
- Market value as on
- 21 Oct 2026
Key policy updates: G.O. Ms. No. 95 and G.O. Ms. No. 16
G.O. updates · January and March 2026Two orders set the rules in Hyderabad, both amending the Telangana Building Rules, 2012. G.O. Ms. No. 16, of 16 January 2026, decides how landowners earn TDR on land affected by lakes, rivers and nalas. G.O. Ms. No. 95, of 21 March 2026, decides how developers use it, and replaced a flat 10% high-rise requirement with slabs.
Mandatory high-rise TDR
A high-rise now means 21 m and above, up from 18 m. For buildings of 10 to 20 floors, 3% of the built-up area above the 10th floor must be loaded with TDR. Above 20 floors it is 5% of the area above the 20th. Down from a flat 10%.
Extra floors and setback relief
Buildings of 18–21 m can now go up through TDR, on plots of about 900–2,400 sq yd (750–2,000 sq m in the order). On plots above 2,400 sq yd, extra floors are allowed depending on the abutting road width. High-rises also get up to 10% relaxation of permissible setbacks, so long as 7 m all round is maintained.
Phased submission
50% of the TDR at building plan approval, the remaining 50% before the Occupancy Certificate.
G.O. Ms. No. 16 · water body lands
TDR for land inside the Full Tank Level of a lake, the Maximum Flood Level of a river, or a notified buffer zone, and for nala widening on private land. Entitlements run from 200% to 400%, set out in the table below.
What is TDR in Hyderabad?
A TDR certificate is issued by GHMC or HMDA and represents built-up area. A landowner receives one when the authority takes their land for a public project (road widening, a nala, a lake buffer, a park) instead of a cash payment. The holder can keep it, use it on their own plot, or sell it to a developer who needs to build beyond the permitted FSI.
How TDR pricing works in Hyderabad
TDR in Hyderabad trades at 58–65% of government market value, and that value is the one for the receiving plot. Look up the rate on IGRS Telangana, multiply, and you have the price.
The simple maths
Government market value × Hyderabad rate × TDR area
- Government market value
- ₹ per sq yd, from IGRS Telangana
- Hyderabad rate
- 58% – 65%
- TDR area
- in sq yd
Government market value
₹ per sq yd, from IGRS Telangana
58% – 65%
Hyderabad rate
TDR area
in sq yd
TDR price
in ₹
Find the government market value
Check the IGRS Telangana portal at registration.telangana.gov.in for the government market value, in ₹ per sq yd, of the receiving plot.
Ledger check
We verify the unused balance on the certificate against the Buildnow TDR portal before matching.
TDR entitlement in Hyderabad
How much TDR the land earns when you surrender it. This is a different percentage from the trading rate above: entitlement is the area you receive, the rate is what it sells for. The four water body rows come from G.O. Ms. No. 16.
Road widening and master plan roads
400%Land surrendered free of cost for proposed master plan roads, link roads or junction improvements
Nala widening and stormwater drains
400%Private land surrendered for widening or developing nalas and drainage channels
Water body conservation, outside buffer zones
400%Land taken for conservation, riverfront projects or water body development
Buffer zones of lakes and rivers
300%Private land inside notified buffer zones surrendered for conservation or green belts
FTL and MFL lands
200%Land inside the Full Tank Level of a lake or the Maximum Flood Level of a river
Parks, playgrounds and public open spaces
200%Land surrendered for public recreational spaces and green zones
Heritage buildings and conservation precincts
100%Surrendering unused vertical development potential to preserve notified heritage structures
Example 1 of 3
Moving TDR between zones (Uppal and Kokapet)
A certificate carries the value of the land it came from, not a fixed number of square yards. Move it to a costlier zone and the usable area shrinks so the value transferred stays the same.
Scenario
An owner surrenders land for road widening in Uppal and receives a certificate for 1,000 sq yd of TDR.
Original plot · Uppal
Certificate issued
- Government market value
- ₹20,000 per sq yd
- Certificate issued
- 1,000 sq yd
Case A · loaded in Uppal
₹20,000 ÷ ₹20,000 = 1.0
- Government market value
- ₹20,000 per sq yd
- Usable TDR
- 1,000 sq yd
Case B · loaded in Kokapet
₹20,000 ÷ ₹80,000 = 0.25
- Government market value
- ₹80,000 per sq yd
- Usable TDR
- 250 sq yd
Why the area changes between zones
The certificate carries the value of the land that was surrendered. Loaded in a costlier area, the usable area falls so that the value transferred stays the same.
Loading in a cheaper zone
The formula runs both ways. A certificate from a high-value zone, loaded in a lower-value one, gives more usable area than the figure printed on it.
What this means for you
Developers should compare certificates by usable area at their own site, not by the area printed on them. Sellers should know the government market value of their original plot, because it decides what the certificate is worth in each part of the city.
Example 2 of 3
Adding two floors, and the cap
G.O. Ms. No. 95 lets a building rise above its standard floor limit by loading TDR, with the ceiling set by the abutting road width. This is the route for non-high-rise and mid-rise buildings. The 3% and 5% slabs in the policy block above are a separate, mandatory charge on high-rises past the 10th floor, not what this example is doing.
Scenario
- Plot size
- 1,000 sq yd
- Road width
- 40 ft
- Permissible base height
- Ground + 3 floors
- Floor plate
- 444 sq yd per floor
- Developer intent
- Two more floors, taking it to Ground + 5

- Cap set by road width
- Added with TDR · about 889 sq yd
- Base height · G + 3
- 1
Work out the extra built-up area
2 floors × 444 sq yd = about 889 sq yd.
- 2
TDR required
A non-high-rise building adding floors within the road width cap surrenders TDR matching the extra area in full: about 889 sq yd, not a percentage of it.
- 3
What it costs
Say the receiving plot's government market value is ₹20,000 per sq yd. At the Hyderabad rate of 58–65%, 889 sq yd of TDR costs about ₹1.03 crore to ₹1.16 crore.
- 4
Phased compliance
- 50% · about 445 sq ydAt building plan approval
- 50% · about 445 sq ydBefore Occupancy Certificate
50%, about 445 sq yd, at building plan approval. The remaining 50% before the Occupancy Certificate.
The cap on extra floors
The road width cap. Road width sets the cap: up to 5 additional floors, against thresholds of 40 ft, 60 ft and 80 ft. A 40 ft road cannot exceed its cap however much TDR the developer holds.
Plot and coverage limits. Minimum plot size and site coverage rules apply alongside. Once the road width cap is reached, no further TDR can be loaded for height.
Example 3 of 3
Using TDR for setback relief instead of floors
A project can meet the permitted floor count and still be short of room for the statutory setbacks alongside floor plates or a ramp. G.O. Ms. No. 95 lets TDR buy that room.
How it works
Up to 10% relaxation of the prescribed setbacks by surrendering equivalent TDR, so long as fire safety clearances are respected.
Scenario
- Building
- High-rise, commercial or residential
- Prescribed setback
- 8 m all round
- Non-negotiable minimum
- 7 m, fire engine driveway
The problem: 0.8 m more needed along one wing for an entry ramp.

- 0.8 m gained with TDR · about 48 sq yd
- Setback
- Fire engine path limit
- 1
Setback relief
A 10% reduction takes the setback from 8.0 m to 7.2 m, keeping the 7 m fire clearance.
- 2
Deficit area
0.8 m × 50 m of building length = about 48 sq yd
- 3
TDR equivalent
Rather than lose floor plate width, the developer buys and surrenders the matching TDR to GHMC or HMDA.
Outcome
Height and floor count are unchanged. The developer gets a larger ground footprint and workable ramp access, within the bye-laws.
Three steps to a deal
- 1
Tell us what you hold or need
Your city, whether you are buying or selling, and the TDR value.
- 2
We verify and match
We check the certificate against GHMC or HMDA records and introduce you to a verified buyer or seller.
- 3
You close the deal
The TDR is transferred in the authority's records, with full documentation. The money moves directly between the two of you.
Sell TDR in Hyderabad
Hold a GHMC or HMDA certificate? We verify it, match you with developers who need TDR in Hyderabad, and you sell at the market rate.
Buy TDR in Hyderabad
Need extra floors or setback relief under G.O. Ms. No. 95? Find verified GHMC and HMDA certificates, priced against the government market value of the receiving plot.
FAQs on TDR in Hyderabad
TDR is built-up area granted in place of cash when you surrender land for a public project: road widening, nala widening, lake conservation, a park, a heritage precinct. In Hyderabad it is issued by GHMC or HMDA, depending on where the land falls.
It depends on why the land was taken. Road widening, nala widening and water body conservation outside buffer zones earn 400% of the surrendered area. Lake and river buffer zones earn 300%. FTL and MFL lands, parks and playgrounds earn 200%. Heritage precincts earn 100%. The water body entitlements were set by G.O. Ms. No. 16 in January 2026. The full table is above.
Square yards. Government market value is published in ₹ per sq yd on IGRS Telangana, and certificates and quotes follow the same unit. Building plans are drawn in square feet, so convert at 9 sq ft to 1 sq yd when you compare a certificate against a floor plate.
At 58–65% of the government market value of the receiving plot. Look the value up on IGRS Telangana in ₹ per sq yd, multiply by the rate, multiply by the TDR area. Where in the band a certificate lands depends on its type, the zone and how much supply is in the market that month.
The usable area is adjusted by the ratio of the two plots' government market values. A certificate for 1,000 sq yd generated in Uppal at ₹20,000 per sq yd gives 1,000 sq yd if loaded in Uppal, but only 250 sq yd if loaded in Kokapet at ₹80,000. The value transferred stays the same; the area does not.
For buildings of 10 to 20 floors, 3% of the built-up area above the 10th floor must be loaded with TDR. Above 20 floors it is 5% of the built-up area above the 20th. The order also moved the high-rise threshold from 18 m to 21 m, and lets buildings of 18–21 m go up via TDR on plots of about 900–2,400 sq yd (750–2,000 sq m in the order).
Yes. 50% at building plan approval, the remaining 50% before the Occupancy Certificate.
Yes, since G.O. Ms. No. 95. High-rise buildings can get up to 10% relaxation of the permissible setbacks by surrendering matching TDR, so long as 7 m is maintained all round. Non-high-rise buildings can get setback relief too, subject to the minimums prescribed for road widening.
We check the certificate against GHMC or HMDA records, confirm the holder's name, confirm the unused balance on the Buildnow TDR portal, and confirm that no lien or dispute is recorded against it. Only then do we introduce the two sides.