The Thiruvananthapuram Angamaly Greenfield Highway was a 257 km, six-lane access-controlled corridor proposed under Bharatmala Pariyojana with a 45 metre right of way running from Pulimath near Kilimanoor to Angamaly in Ernakulam.
The Union Ministry told Parliament in February 2025 that the project has been halted, though a DPR is on record and MoEF&CC alignment approval was received in 2023. This overlay maps the notified alignment across six Kerala districts.
This page covers what the current status means for anyone who bought "expressway-adjacent" land, the Kerala paddy law overlay, and the exact checks now required.
Two facts drive every buyer decision on this corridor today. First, the Thiruvananthapuram Angamaly Greenfield Highway alignment was approved by the Ministry of Environment in 2023, and NHAI had begun collecting land acquisition compensation deposits before Nitin Gadkari confirmed in Parliament that the project stands halted.
Second, Kerala's own Conservation of Paddy Land and Wetland Act, 2008 runs on top of any highway proposal. If the plot is nilam in the Land Data Bank, no highway approval fixes that.
The table below shows the document stack every buyer must verify along the notified corridor.
Document / Register
What It Governs
Required Before Purchase?
Common Trap
NHAI 3(A) / 3(D) notification
Highway acquisition strip (45m RoW)
Confirm survey number status
Brokers still selling as "expressway-adjacent"
Land Data Bank (LDB) entry
Paddy or wetland classification
Krishi Bhavan LDB check
Purayidam claim vs nilam record
Form 6 conversion (under 20.23 Ares)
Small-plot use change
RDO sanction under KLU Order
Sold as pending, never granted
Section 27A permission
Unnotified paddy conversion
RDO order
Assumed automatic
Village Office BTR extract
Revenue category
Village Office
Old BTR without correction
Kerala Land Records Portal (Bhulekh)
Digital land record
e-district or Village Office
Outdated survey number entry
Document / Register
What It Governs
Required Before Purchase?
Common Trap
NHAI 3(A) / 3(D) notification
Highway acquisition strip (45m RoW)
Confirm survey number status
Brokers still selling as "expressway-adjacent"
Land Data Bank (LDB) entry
Paddy or wetland classification
Krishi Bhavan LDB check
Purayidam claim vs nilam record
Form 6 conversion (under 20.23 Ares)
Small-plot use change
RDO sanction under KLU Order
Sold as pending, never granted
Section 27A permission
Unnotified paddy conversion
RDO order
Assumed automatic
Village Office BTR extract
Revenue category
Village Office
Old BTR without correction
Kerala Land Records Portal (Bhulekh)
Digital land record
e-district or Village Office
Outdated survey number entry
If any seller on this corridor is still quoting appreciation on the strength of the greenfield highway, treat that as the red flag. As of the February 2025 statement in Parliament, no approval, no tender, and no concrete Vision 2047 replacement corridor exists on record. Verify the current MoRTH position and the plot's LDB entry independently before releasing any advance.
The 257 km alignment was designed to sit on the eastern side of Main Central Road (SH-1) through 13 taluks across six districts. That parallel positioning is what created the strongest speculation belts. Buyers should now separate three categories: the notified corridor itself, land where NHAI had already deposited compensation before the halt, and adjoining farmland that was priced up purely on expressway proximity.
The table below sorts the notable localities along the Pulimath to Angamaly alignment.
Corridor / Locality
District
Taluk
Current Buyer Concern
Pulimath, Kilimanoor
Thiruvananthapuram
Chirayinkeezhu
Notification still on record, project halted
Kadakkal, Kottarakkara, Punalur, Pathanapuram
Kollam
Kottarakkara, Punalur, Pathanapuram
Speculative pricing without construction
Konni, Ranni
Pathanamthitta
Konni, Ranni
Forest and slope classification adjacent
Kanjirappally, Meenachil (Palai)
Kottayam
Kanjirappally, Meenachil
Plantation land marketed as buildable
Thodupuzha
Idukki
Thodupuzha
Rubber-heavy zone, forest buffer
Muvattupuzha, Kothamangalam, Kunnathunad, Angamaly
Ernakulam
Multiple
Airport-adjacent premium already priced in
Corridor / Locality
District
Taluk
Current Buyer Concern
Pulimath, Kilimanoor
Thiruvananthapuram
Chirayinkeezhu
Notification still on record, project halted
Kadakkal, Kottarakkara, Punalur, Pathanapuram
Kollam
Kottarakkara, Punalur, Pathanapuram
Speculative pricing without construction
Konni, Ranni
Pathanamthitta
Konni, Ranni
Forest and slope classification adjacent
Kanjirappally, Meenachil (Palai)
Kottayam
Kanjirappally, Meenachil
Plantation land marketed as buildable
Thodupuzha
Idukki
Thodupuzha
Rubber-heavy zone, forest buffer
Muvattupuzha, Kothamangalam, Kunnathunad, Angamaly
Ernakulam
Multiple
Airport-adjacent premium already priced in
The most misread pocket is the Ernakulam end. Buyers assume Angamaly's proximity to Kochi International Airport plus the greenfield highway would drive certain uplift. With the highway now halted and only the Angamaly-Kundannoor bypass moving forward, the airport is the driver, not the greenfield corridor.
Confirm the current project status directly with NHAI Kottayam Project Director office before treating any Muvattupuzha or Kothamangalam parcel as corridor land.
For Land Owners & Agents
I want to sell my land in Kerala
10:32
Plz share your Land's location - We will list it on 1acre map, for Free.
10:32

250 Sq yds
2.5 Acres
For Land Buyers
Every listing goes through our Preliminary Verification Process.

View Kannur Masterplan as a live map overlay – check any plot's land use zone for free on 1acre.in. Kannur City Master P...

View Kollam Masterplan as a live map overlay – check any plot's land use zone for free on 1acre.in. Kollam City Masterpl...

View Kozhikode Masterplan as a live map overlay – check any plot's land use zone for free on 1acre.in. Kozhikode masterp...

View Kannur Masterplan as a live map overlay – check any plot's land use zone for free on 1acre.in. Kannur City Master P...

View Kollam Masterplan as a live map overlay – check any plot's land use zone for free on 1acre.in. Kollam City Masterpl...

View Kozhikode Masterplan as a live map overlay – check any plot's land use zone for free on 1acre.in. Kozhikode masterp...
No, not currently. In February 2025, the Union Minister of Road Transport and Highways told Parliament that the project has been halted, and NHAI has stopped further procedures. A DPR exists on record, but no active tender or construction timeline is in place.
The alignment was 257 km, six-lane access-controlled greenfield, running with a 45-metre right of way from Pulimath in Chirayinkeezhu taluk to Angamaly in Ernakulam. It was designed to run parallel to Main Central Road (SH-1) on the eastern side.
The alignment passes through six districts: Thiruvananthapuram, Kollam, Pathanamthitta, Kottayam, Idukki, and Ernakulam, across 13 named taluks including Kottarakkara, Punalur, Konni, Ranni, Kanjirappally, Meenachil, Thodupuzha, Muvattupuzha, Kothamangalam, and Kunnathunad.
Yes, NHAI had initially collected acquisition-related deposits, but funds could only be released after project clearance. When Gadkari confirmed the halt, the compensation and acquisition process were suspended, leaving affected landholders in an unresolved position.
No, not directly. If the parcel is listed as nilam in the Land Data Bank, it cannot be sold as buildable. Conversion under Section 27A Form 6 conversion or the KLU Order route requires prior Revenue Divisional Officer sanction.
No. A high-speed corridor was mentioned under the Centre's Vision 2047 initiative as a possible alternative, but no alignment, DPR, or notification has been issued. Any broker citing a Vision 2047 replacement route is speculating.
The current Bhulekh Kerala RoR, Land Data Bank status, BTR at the Village Office, and a fresh No Objection Certificate from the local NHAI Project Implementation Unit confirming the survey number is no longer under active 3(A) notification.
The 257 km alignment was designed to run from Pulimath near Kilimanoor to Angamaly in Ernakulam, sitting on the eastern side of Main Central Road (SH-1) through 13 taluks across six districts. Treat it as a proposed alignment only, since the Ministry confirmed in Parliament that the project stands halted.
Source
Official government land and infrastructure records
Official Website
document.kerala.gov.in
Coordinate Reference System
EPSG:4326 (WGS 84)