Bengaluru STRR (NH-948A) – Phase Status and Land-Buying Guide

NHAI

Road
Bengaluru STRR (NH-948A) – Phase Status and Land-Buying Guide map

Overview

Bengaluru STRR land buying decisions require knowing which of the three phases is operational, which is legally frozen, and which localities sit inside the 1,019 sq km STRR Planning Authority jurisdiction. The Satellite Town Ring Road (NH-948A) is a 280.8 km access-controlled expressway under NHAI connecting 12 satellite towns under the Bharatmala Pariyojana. Phase 1 (Dobaspete to Hoskote, 80 km) was inaugurated on March 11, 2024 at a combined cost of over ₹2,750 crore (per NHAI award figures; verify against contract notification). Phase 2 is on hold. This page covers what that hold means for plots in and around Kanakapura and Anekal, and which corridors carry verified title and conversion status.

Phase II is on Hold Because of Bannerghatta: What That Means for Plots Near Anekal and Kanakapura

Phase 2 of the STRR, the 56 km section that passes through the eco-sensitive zone (ESZ) of Bannerghatta National Park (km 95.525 to km 138.0), is officially on hold. NHAI has confirmed this publicly. The alignment requires a 3.85 km elevated viaduct through the park's core zone plus ~2 km through the buffer (per Citizen Matters / NHAI feasibility), with a 28.5 m right-of-way, plus the diversion of 11 hectares of forest from the core zone and 5.7 hectares from the buffer zone. Forest clearance from the Forest Conservation Authority was still pending at the time of writing; MoEFCC had issued terms of reference but the final forest diversion approval had not been granted.

This affects buyers in the Anekal, Kanakapura, and south-western STRR corridor directly. The upside thesis for these localities is real: Phase 3 (western packages: Somakkanamutta to Kunigal, Kunigal to Thattekere, Thattekere to Bagganadoddi) is being executed ahead of Phase 2. But a buyer purchasing agricultural land in the Anekal-Attibele belt on the assumption that Phase 2 will be operational by a specific date is carrying regulatory risk that is not priced into current broker conversations.

The land title risk along the full STRR corridor is a separate and equally serious issue. The STRR passes through 331 villages. Agricultural land near STRR interchanges requires DC conversion before it can be used for residential or commercial development. A Gram Panchayat layout approval is not a substitute for DC conversion. Under Karnataka law, the Gram Panchayat has no authority to sanction a layout on unconverted agricultural land; any such approval is legally invalid and does not provide A-Khata status or bank loan eligibility.

The Karnataka Land Revenue (Amendment) Rules, 2025,notified in September 2025 and finalized on 23 December 2025 after public consultation, modernised the conversion process but did not change the fundamental requirement: agricultural land must carry a valid DC conversion order before any non-agricultural use or layout development.

Phase 1 (Pkg 1)

Section

Dobaspete to Doddaballapur bypass

Length

42 km

Status (early 2026)

Inaugurated March 2024 (toll collection from June 2024)

Primary Buyer Risk

Plots without DC conversion or BMRDA approval

Phase 1 (Pkg 2)

Section

Doddaballapur to Hoskote

Length

37.6 km

Status (early 2026)

Inaugurated March 2024 (toll collection from Nov 2023)

Primary Buyer Risk

Same as above

Phase 2

Section

Bannerghatta National Park ESZ section

Length

56 km

Status (early 2026)

On hold; MoEF&CC and National Wildlife Board cleared, Forest Conservation Authority (FCA) clearance pending

Primary Buyer Risk

Corridor completion timeline uncertain; price expectations not anchored

Phase 3 (5 pkgs)

Section

Somakkanamutta to Ramanagara, Kunigal to Thattekere area

Length

144 km

Status (early 2026)

Tenders issued Sept 2024; ₹4,750 crore

Primary Buyer Risk

Agricultural land without conversion; some parcels in acquisition zone

The practical rule for Bengaluru STRR land buying is this: proximity to an STRR interchange does not give agricultural land residential use rights. DC conversion does.

Devanahalli, Hoskote, Doddaballapur and Sarjapur: How STRR Phase Status Affects Plot Decisions

The STRR Planning Authority, set up by the Karnataka government in 2016, covers a planning area of 1,019 sq km across the 12 satellite towns. Within this jurisdiction, layout approvals flow through local planning authorities under BMRDA, including Anekal, Hoskote, Kanakapura, Nelamangala, and Ramanagara, not through Gram Panchayats. For Bengaluru STRR land buying, the approval chain to verify is: DC conversion order, local planning authority layout sanction, and RERA registration for plotted developments with 8 or more plots.

The four corridors with the strongest sourced investment rationale are Devanahalli (north), Hoskote (east), Doddaballapur (north-west), and Sarjapur (south-east). Devanahalli carries airport-led demand from Kempegowda International Airport plus the Aerospace Park and ITIR designation. The NH-44 expansion around Devanahalli links directly to the STRR Phase 1 operational section. Hoskote is the eastern terminus of operational Phase 1 and connects to the Bengaluru-Chennai Expressway (NE-7), making it a logistics and industrial hub. Doddaballapur benefits from both the operational STRR bypass and an established textile industry base. Godrej Properties acquired a 48-acre parcel near the STRR in this belt in 2025 for a plotted residential development with approximately 1.1 million sq ft of development potential. Sarjapur is the south-eastern node: an established IT residential market that gains from STRR decongesting the ORR.

Devanahalli

STRR Section

Phase 1 (operational)

Infrastructure & Economic Drivers

Airport, Aerospace Park, ITIR

Current Approval Route

BIAAPA layout approval; BDA for some pockets

Key Risk

Hi-tech zone acquisition risk; check master plan

Hoskote

STRR Section

Phase 1 (operational)

Infrastructure & Economic Drivers

Logistics, Bengaluru-Chennai Expressway, industrial

Current Approval Route

Hoskote Planning Authority under BMRDA

Key Risk

Agricultural plots without conversion widely marketed

Doddaballapur

STRR Section

Phase 1 (operational)

Infrastructure & Economic Drivers

Textile industry, logistics, Multi-Modal Logistics Park at Dobaspete

Current Approval Route

BMRDA local planning authority

Key Risk

Revenue sites and Gram Panchayat layouts still common

Sarjapur

STRR Section

Phase 3 (under construction)

Infrastructure & Economic Drivers

IT residential spillover from Whitefield; ORR decongestion

Current Approval Route

BMRDA, Anekal Planning Authority

Key Risk

Phase 3 completion timeline tied to Bannerghatta clearance

Sarjapur is the most commonly misread corridor. Buyers price Sarjapur plots at STRR-connectivity valuations even though the relevant STRR section (Phase 3 southern package near Attibele and Anekal) is still under construction and the adjacent Phase 2 Bannerghatta section remains on hold. The ORR already serves Sarjapur directly. STRR adds a second connectivity layer once Phase 3 is complete, but that completion depends on resolution of the Bannerghatta clearance issue.

Data Source & Verification

Source

NHAI — Bharatmala Pariyojana project documents

Official Website

nhai.gov.in

Coordinate Reference System

EPSG:4326 (WGS 84)

Geometry Type

Polygon / MultiPolygon

Data Format

Vector (GeoJSON) + Raster Tiles

Last Verified

April 2026

Status

Active

Disclaimer: Alignment and corridor information shown here is indicative. Users should verify details with NHAI (National Highways Authority of India) at nhai.gov.in or the relevant local planning authority before any transaction or development decision.

Frequently Asked Questions