Mancherial - Warangal Expressway
NHAI

Overview
The Mancherial-Warangal Expressway is a 108-km, four-lane access-controlled greenfield highway on NH-163G, forming the central Telangana section of the 405-km Nagpur-Vijayawada Economic Corridor under Bharatmala Pariyojana Phase-I. NHAI contracted all three construction packages to Megha Engineering and Infrastructures Ltd. (MEIL) in March 2023 at a combined cost of ₹3,441 crore. The corridor starts at Narva village in Jaipur mandal, Mancherial, and ends at Oorugonda village near Warangal. As of January 2025, all three packages remain in the "awarded but not started" category in NHAI's official records.
Contracts Awarded in 2023, Still Not Started in 2025: The Land Acquisition Blockage on NH-163G
A contract award by NHAI does not mean land acquisition is complete. That distinction is the single most important fact for anyone buying near this corridor.
All three Mancherial-Warangal packages were awarded to MEIL in March 2023 with a two-year construction deadline. As per NHAI's own project status document dated January 2025, all three remain "awarded but not started." The reason is land acquisition. The NH-163G corridor, covering approximately 275 km across Telangana, was flagged as a major casualty of stalled land acquisition in a letter from Union Minister G. Kishan Reddy to the Telangana Chief Minister in March 2023. The Mancherial-Warangal section (₹3,441 crore) was explicitly named as one of the blocked projects.
The compensation dispute compounds the delay. In July 2024, lawyers representing farmers whose land was notified for the 108-km corridor from Narva to Oorugonda submitted representations to the Mancherial Collector, arguing that land compensation rates had not been revised since 2013. Under the National Highways Act, compensation is based on market value at the time of the Section 3A notification, assessed using the previous three years' sale data. When those reference values are frozen at 2013 prices, farmers in a district where coal-belt land values have moved significantly receive compensation that bears no relationship to current market price. The Telangana CM held a review meeting in September 2025 and ordered all pending highway land acquisition cases to be resolved by October 2025, but as of that review, court cases were still pending in multiple districts and compensation fund release from NHAI's competent authority remained delayed.
The table below shows the three construction packages under which MEIL holds contracts for the Mancherial-Warangal section.
I
Stretch
Narva (Ch.3.834 km) to Puttapaka (Ch.35.300 km)
Length
31.5 km
Contract Value
₹873.36 crore
II
Stretch
Puttapaka (Ch.35.300 km) to Pangidipalle (Ch.72.350 km)
Length
37.1 km
Contract Value
₹881.57 crore
III
Stretch
Pangidipalle (Ch.72.350 km) to Oorugonda (Ch.112.240 km)
Length
39.9 km
Contract Value
\\[VERIFY: not disclosed in sources\\]
Package
Stretch
Length
Contract Value
I
Narva (Ch.3.834 km) to Puttapaka (Ch.35.300 km)
31.5 km
₹873.36 crore
II
Puttapaka (Ch.35.300 km) to Pangidipalle (Ch.72.350 km)
37.1 km
₹881.57 crore
III
Pangidipalle (Ch.72.350 km) to Oorugonda (Ch.112.240 km)
39.9 km
\\[VERIFY: not disclosed in sources\\]
Any plot in Narva, Jaipur mandal, Puttapaka, or Pangidipalle that sits within the greenfield acquisition strip has been notified for acquisition and carries a live compensation claim. The High Court has received land acquisition cases from this corridor. A buyer who purchases within the notified strip after the Section 3A notification date does not inherit the compensation; that right stays with the original owner at notification time.
Narva to Oorugonda: Where the Investment Case Is Real and Where It Is Not
The greenfield nature of this highway is its defining investment characteristic. Unlike a brownfield upgrade that widens an existing road, this corridor cuts entirely new land between Mancherial and Warangal. That means the acquisition strip is not alongside a road you can see today. It runs through agricultural land across Jaipur mandal in Mancherial district and extends through villages into Hanamkonda district near Warangal. Plots that look untouched today may sit directly inside a boundary that has been gazette-notified and is pending physical handover.
The legitimate investment zone is land outside the acquisition strip, with full NALA conversion done. Under the Telangana Non-Agricultural Lands Assessment Act of 1963, no agricultural land can be used for residential, commercial or industrial purposes without prior conversion approval from the Revenue Officer. In non-GHMC areas like Mancherial and Warangal districts, the NALA tax is 9% of the basic value of the land. Applications go through MeeSeva centres, with the Tahsildar as the competent authority. If this step is skipped, you cannot legally obtain building permission, a layout approval, or factory clearance on the same plot.
The table below maps zones along the NH-163G Mancherial-Warangal corridor by investment risk.
Narva-Jaipur mandal fringe
Corridor Exposure
Package I start point; greenfield acquisition notified
Primary Risk
Compensation dispute; acquisition not complete
Status
High risk
Puttapaka-Pangidipalle mid-corridor
Corridor Exposure
Packages I-II junction; all ag land
Primary Risk
NALA conversion mandatory; acquisition active
Status
High risk
Oorugonda periphery near Warangal
Corridor Exposure
Package III endpoint; Warangal city fringe
Primary Risk
Less acquisition risk at periphery; check survey number against gazette
Status
Moderate
Mancherial town fringe (Narva exit side)
Corridor Exposure
Adjacent to corridor start, outside greenfield strip
Primary Risk
NALA conversion needed; clear of acquisition if survey number verified
Status
Moderate
Zone
Corridor Exposure
Primary Risk
Status
Narva-Jaipur mandal fringe
Package I start point; greenfield acquisition notified
Compensation dispute; acquisition not complete
High risk
Puttapaka-Pangidipalle mid-corridor
Packages I-II junction; all ag land
NALA conversion mandatory; acquisition active
High risk
Oorugonda periphery near Warangal
Package III endpoint; Warangal city fringe
Less acquisition risk at periphery; check survey number against gazette
Moderate
Mancherial town fringe (Narva exit side)
Adjacent to corridor start, outside greenfield strip
NALA conversion needed; clear of acquisition if survey number verified
Moderate
The most misunderstood investment pitch on this corridor is farmland near Puttapaka or Pangidipalle, sold as "adjacent to the expressway." On a fully greenfield alignment, adjacent to the road means adjacent to the acquisition strip, not adjacent to infrastructure that already exists. Until NHAI completes land handover and MEIL begins physical work, those plots carry both acquisition risk and NALA risk simultaneously.
Frequently Asked Questions
What is the current status of the Mancherial-Warangal Expressway land buying situation?
Contracts for all three packages were awarded to MEIL in March 2023 at ₹3,441 crore. As of January 2025, all three remain in the "awarded but not started" status per NHAI's official records, blocked by land acquisition delays and compensation disputes.
Why has construction not started despite contracts being awarded in March 2023?
Land acquisition is incomplete. Compensation rates for the notified stretch have not been revised since 2013, and farmers representing affected villages submitted formal objections to the Mancherial Collector in July 2024. Court cases are also pending in multiple districts along the NH-163G alignment in Telangana.
Which villages are inside the NH-163G Mancherial-Warangal acquisition strip?
The greenfield corridor runs from Narva village in Jaipur mandal, Mancherial to Oorugonda village near Warangal, passing through Puttapaka and Pangidipalle. If your survey number falls within the notified alignment, verify it against the Section 3A gazette notification before any purchase.
Is NALA conversion required for agricultural land near the Mancherial-Warangal corridor?
Yes. Under the Telangana NALA Act of 1963, all agricultural land requires conversion permission before residential, commercial or industrial use. In non-GHMC districts like Mancherial and Warangal, the conversion tax is 9% of the land's basic value, applied through a MeeSeva centre application.
How is NH-163G land acquisition compensation calculated in Telangana?
Compensation is based on market value at the time of the Section 3A notification, calculated from the previous three years' registered sale transactions for comparable land. Farmers can seek enhanced compensation through arbitration under Section 3G of the National Highways Act if they dispute the award.
Can I safely buy land near Narva or Puttapaka on the NH-163G alignment?
Not without verifying the survey number against the gazette notification first. Both villages are inside the active greenfield acquisition strip. Any plot within that boundary remains subject to acquisition regardless of when you purchased it, as long as the Section 3A notification was published before your sale deed.
What is the total project cost and who is building the Mancherial-Warangal section?
The Mancherial-Warangal section of NH-163G is priced at ₹3,441 crore. Megha Engineering and Infrastructures Ltd. (MEIL) holds all three construction package contracts, awarded in March 2023 under the Hybrid Annuity Model.
Is buying land near the Mancherial-Warangal Expressway a good investment right now?
Only outside the acquisition strip, with confirmed NALA conversion status and a verified survey number. The corridor is real, the contracts are real, but construction has not commenced. Plots inside the notified greenfield strip carry legal title risk that cannot be resolved until NHAI completes land handover.
Disclaimer
Data Source & Verification
Source
Official National Highways Authority of India (NHAI) documents
Official Website
www.nhai.gov.in
Coordinate Reference System
EPSG:4326 (WGS 84)
Geometry Type
LineString / MultiLineString
Data Format
Vector (GeoJSON) + Raster Tiles
Last Verified
2026
Status
Active
