Khammam - Vijayawada Expressway

Khammam - Vijayawada Expressway map

Khammam Vijayawada Expressway Preview

24-Hour Free Access

Try the Khammam - Vijayawada Expressway on the map

Sign in once and explore the layer for a full day.

  • No card details needed
  • Find nearby verified lands for sale

Overview

The Khammam Vijayawada Expressway, designated NH-163G, is an 89.43 km four-lane access-controlled greenfield highway forming the southern segment of the 405 km Nagpur-Vijayawada Economic Corridor under Bharatmala Pariyojana Phase-I. Construction contracts worth Rs. 2,155 crore were awarded to DRA Infra and MEIL in April 2023 across three packages. The corridor passes through both Telangana and Andhra Pradesh, terminating at Jakkampudi on NH-16 near Vijayawada.

The three construction packages are being executed under HAM (Hybrid Annuity Model).

Land Acquisition Freeze Zones: The Hidden Risk in NH-163G Corridor Plots

The single biggest trap in Khammam Vijayawada Expressway land buying is purchasing inside an active acquisition band without knowing it. Under the National Highways Act, once NHAI (National Highways Authority of India) issues a 3(A) notification, the affected land is legally frozen. Owners cannot sell, subdivide, or develop it until the process concludes.

The Gazette of India notification for the Warangal-Khammam section was already published, and similar notifications for the Khammam-Vijayawada section followed. Brokers operating in villages like V. Venkatayapalem, Brahmanapalli, and Remidicherla have been found selling parcels after the 3(A) notification without disclosing its existence to buyers. A registered sale deed does not protect you from acquisition proceedings that were already initiated before you purchased.

The table below shows the three civil packages and their village-level extents, as recorded in official NHAI tender documents.

Package

From Village

To Village

Approx. Length

Contractor (LOA)

1

V. Venkatayapalem (Ch. 220.480 km)

Brahmanapalli(K) (Ch. 250.400 km)

~29.9 km

DRA Infra (Rs. 747 cr)

2

Brahmanapalli(K)

Remidicherla (Ch. 280.200 km)

~29.8 km

MEIL (Rs. 662.66 cr)

3

Remidicherla (Ch. 280.200 km)

Jakkampudi on NH-16 (Ch. 309.909 km)

~29.7 km

MEIL (Rs. 745.83 cr)

Before you sign any agreement for land in these talukas, ask your seller for the survey number and cross-reference it against the NH-163G DPR alignment on the 1acre map. If the survey number falls within 100 metres of the greenfield corridor centerline, treat it as inside the acquisition zone until a lawyer confirms otherwise.

Growth Corridors and Micro-Markets Along the Khammam-Vijayawada Greenfield Alignment

Not every parcel on this corridor is a risk. Land sitting just outside the acquisition band but within 2-5 km of a confirmed interchange has historically performed well once construction enters the physical work stage. The Khammam Vijayawada Expressway creates three distinct micro-market tiers worth tracking.

The first is the Jakkampudi node at the Vijayawada end. Forum discussions and Andhra Pradesh planning documents confirm that Jakkampudi will serve as the point where the new NH-163G connects to NH-16, effectively making it a junction for both the Vijayawada West Bypass and the new Nagpur corridor. Land within 3 km of this node is already attracting early investor attention. The second tier covers the Khammam fringe belt, particularly near V. Venkatayapalem, where Package 1 originates. Agriculture Minister Tummala Nageswara Rao stated in July 2024 that land near Khammam on this alignment is among the costliest affected parcels, which confirms market participants have already priced in part of the upside. The third tier covers mid-corridor villages around the Remidicherla area in Krishna district, where land prices have not yet moved in line with the terminal nodes.

Micro-Market

Tier

Primary Driver

Key Risk

Jakkampudi (Krishna dist.)

High

NH-163G/NH-16 junction + Vijayawada West Bypass

Land already priced; verify survey number not in acquisition

V. Venkatayapalem (Khammam dist.)

Medium

Package 1 origin, regional connectivity

Active land acquisition proceedings underway

Remidicherla belt (Krishna dist.)

Early-stage

Mid-corridor appreciation lag

DPR alignment not fully demarcated on ground

Brahmanapalli (Telangana-AP border)

Speculative

Cross-state corridor node

Delayed construction timeline; land acquisition stalled

The most misunderstood corridor here is the Brahmanapalli belt. Because it sits at the Telangana-Andhra Pradesh state border, it falls under the jurisdiction of two state governments simultaneously. Land acquisition disputes on this stretch contributed to delays flagged in a March 2023 Business Standard report, and physical work had not commenced as of late 2024. Buying here requires clarity on which state's Dharani or registration portal carries the current patta, and whether the survey number sits on the Telangana or the AP side of the boundary.

Was this layer helpful?

Anything wrong, outdated, or missing we want to hear it.

For Land Owners & Agents

Looking to sell your land in Telangana?

I want to sell my land in Hyderabad

10:32

Plz share your Land's location - We will list it on 1acre map, for Free.

10:32

For Land Buyers

Browse all verified lands & plots in Telangana

View on Map