Orange Gate to Marine Drive underground twin tunnel, Mumbai

Orange Gate to Marine Drive underground twin tunnel, Mumbai map

Orange Gate Marine Drive Underground Twin Tunnel Preview

24-Hour Free Access

Try the Orange Gate to Marine Drive underground twin tunnel, Mumbai on the map

Sign in once and explore the layer for a full day.

  • No card details needed
  • Find nearby verified lands for sale

Overview

Orange Gate Marine Drive Tunnel Mumbai refers to MMRDA's underground twin-tunnel road project connecting the Eastern Freeway at Orange Gate to Marine Drive near Churchgate, running beneath South Mumbai's island city at depths of up to 52 metres. MMRDA gives the corridor length as 9.96 km, of which about 7 km is underground. The Orange Gate-Marine Drive Underground Twin Tunnel is a live map layer on 1acre. Approved at a cost of roughly Rs 8,056 crore, with tunnelling launched by the Chief Minister on 3 December 2025 and a targeted completion of December 2028, the project runs beneath nearly 700 buildings, including over a hundred heritage structures, several railway corridors, and Metro Line 3. This page covers where Orange Gate is, the route and project details, the realignment debate triggered by heritage-area residents and the revised Marine Drive exit cleared by the state coastal authority in June 2026, and what that signals for anyone with property interests near the route.

Where is Orange Gate in Mumbai

Orange Gate is a gate of the Mumbai Port area on P D'Mello Road in South Mumbai, at the southern end of the Eastern Freeway. Searches for 'Orange Gate, MbPT' use the short form of Mumbai Port Trust, the port body the gate belongs to; the area is now under the Mumbai Port Authority. For drivers, Orange Gate is the southern end of the Eastern Freeway, which runs north towards Chembur and links to the Atal Setu (Mumbai Trans Harbour Link).

Orange Gate is where the tunnel begins. MMRDA launched its tunnel boring machine (TBM) at Orange Gate on 3 December 2025, and the 2023 project design provides a viaduct at Orange Gate for vehicle access into the tunnel. From there the twin tunnels run west beneath the railway corridors, Metro Line 3 and the dense, heritage-rich streets of the island city to Marine Drive, where they connect with the Mumbai Coastal Road.

Question

Answer

Where is Orange Gate in Mumbai?

On P D'Mello Road, in the Mumbai Port area of South Mumbai

What is it known for?

Southern end of the Eastern Freeway

Tunnel role

Eastern end of the tunnel; TBM launch site

Other end of the tunnel

Marine Drive, linking to the Mumbai Coastal Road

For property buyers, Orange Gate is an established port and freeway node. The surface changes here are the tunnel approach and the road widening at the Eastern Freeway end that MMRDA included in its revised design, rather than fresh land acquisition.

Orange Gate to Marine Drive tunnel route map

The Orange Gate to Marine Drive tunnel route map is easiest to read as a line from the Eastern Freeway in the east to Marine Drive in the west, deep below the island city. MMRDA's figures give a 9.96 km corridor with about 7 km underground, at depths of 12 to 52 metres. The table lists the entry and exit points, connecting roads and the main structures the tunnel passes beneath, in order from Orange Gate.

From Orange Gate

Point or feature

What happens there

1

Orange Gate, P D'Mello Road (Eastern Freeway end)

Eastern entry and exit; viaduct access; TBM launched December 2025

2

Central and Harbour Railway tracks

TBM crossed seven operational tracks without stopping train services (reported August 2026)

3

Metro Line 3 (Aqua Line) and Western Railway corridor

Tunnel passes beneath both; under Metro Line 3 at a depth of over 50 metres

4

South Mumbai island city

Runs under about 700 buildings, including over 100 heritage structures; the 2023 design described the alignment as mainly under Sardar Vallabhbhai Patel Road

5

Marine Drive, original plan

Exit after B D Somani Chowk, near Wankhede Stadium

6

Marine Drive, revised design

Western exit moved north, near Saifee Hospital towards Girgaum Chowpatty; coastal clearance granted in June 2026

7

Mumbai Coastal Road

Onward connection from Marine Drive

MMRDA has not published a detailed public route map of the revised alignment, and this page does not host one. View the alignment on the 1acre map layer, and check the exit position against the latest MMRDA notice before relying on it for a specific building.

Orange Gate tunnel project details

MMRDA (Mumbai Metropolitan Region Development Authority) is building the Orange Gate tunnel project as a twin-tube road tunnel. The figures below are those MMRDA gave at the tunnelling launch in December 2025 and in later progress reports. Earlier reports cited different lengths (9.23 km and 9.5 km in 2023) and costs (Rs 7,765 crore and Rs 7,500 crore), mainly because the design has been revised.

Detail

Figure

Authority

MMRDA

Contractor

Larsen & Toubro (L&T), contract awarded in 2023

Project cost

Rs 8,056 crore

Corridor length

9.96 km, about 7 km of it underground

First tunnel under construction

About 3.45 km

Depth

12 to 52 metres

Lanes

Two traffic lanes and one emergency lane per tube; 80 km/h limit

Tunnel boring machine

Slurry shield, 12.19 m cutterhead, about 82 m long

Launch

3 December 2025

Main tunnelling began

28 February 2026

Progress

About 650 metres excavated by July 2026

Southbound tunnel to Marine Drive

Target December 2027

Project completion

Target December 2028

Travel time once open

About five minutes, Orange Gate to Marine Drive

As of October 2026, the latest published update, in August 2026, reported that the TBM had passed beneath seven Central and Harbour Railway tracks with trains running. The main open approval is the Union Environment Ministry's decision on the seaward promenade extension at Marine Drive.

Marine Drive's heritage objections and the revised tunnel exit

Within a week of the Chief Minister launching the tunnel boring machine, MMRDA began considering altering the tunnel's alignment following strong objections from Marine Drive residents.

The Marine Drive Citizens Association raised concerns that the original alignment, connecting Orange Gate under the Mumbai Port Authority to D Road near Churchgate adjacent to Wankhede Stadium, would disturb the iconic Art Deco heritage precinct, worsen construction-phase traffic, and cause air pollution.

Residents specifically criticised the original Opera House entry point as impractical, and MMRDA reportedly considered alternatives including reclaiming land beyond the National Centre for Performing Arts, routing the alignment outside NCPA entirely, or positioning tunnel entry points near Oval Maidan instead.

Concern Raised

What Residents Argued

MMRDA's Response

Heritage building safety

Original alignment risked structural implications not adequately studied

Considering alternative, "safer and less intrusive" locations

Opera House entry point

Termed impractical by residents

To be replaced under a new proposal

Construction-phase disruption

Traffic diversions and air pollution concerns near the heritage stretch

Alternative alignments including NCPA-adjacent options under discussion

This is not the Marine Drive Precinct's first fight over development near its heritage buildings. Residents previously took the BMC and Maharashtra's Urban Development Department to the Bombay High Court over a proposal to double building heights in the precinct, arguing it would destroy the value and integrity of the area's Art Deco heritage and jeopardise Mumbai's UNESCO World Heritage nomination bid. That litigation forced the civic body to hold off enforcing its guidelines pending a Supreme Court decision on a related petition. Given this precedent, any property owner near the tunnel's southern portal should track MMRDA's finalised route rather than the originally announced one.

Update: the revised Marine Drive exit (October 2026)

In April 2026 MMRDA proposed moving the tunnel's western exit north, from near Wankhede Stadium to the area near the PM Hindu Swimming Bath and Boat Club, close to Girgaum Chowpatty, to spread exiting traffic along Marine Drive. The Maharashtra Coastal Zone Management Authority (MCZMA) cleared the revised design at its meeting on 16 June 2026, with conditions on traffic management, noise barriers and low-tide construction. The design reorganises Marine Drive's lanes, with three dedicated lanes for vehicles leaving the tunnel towards Nariman Point, and addresses a bottleneck near Saifee Hospital at the tunnel's western exit. A seaward extension of the promenade, about 120 metres long, needs final approval from the Union Environment Ministry because it falls in the intertidal zone.

What This Means for Property Near the Tunnel Route

The tunnel itself runs almost entirely underground and requires no large-scale surface land acquisition of the kind seen on typical highway projects, but its two portals, at Orange Gate and near Marine Drive/Churchgate, are exactly where surface-level property impact concentrates.

Location

Relevance

Known Risk

Orange Gate (Eastern Freeway terminus)

Northern tunnel portal, connects to existing elevated freeway

Established infrastructure node; limited fresh land acquisition needed

Marine Drive / Churchgate / D Road

Original southern portal area, adjacent to Wankhede Stadium and NCPA

Exit moved north under the revised design cleared by MCZMA in June 2026

Marine Drive near Saifee Hospital / Girgaum Chowpatty

Revised western exit

Lane changes on Marine Drive and a promenade extension that still needs central approval

Marine Drive Art Deco precinct

Heritage-protected zone directly above/adjacent to the tunnel route

Any redevelopment here has a documented history of litigation over height and heritage rules

CSMT and railway corridor crossing

Tunnel passes beneath Chhatrapati Shivaji Maharaj Terminus at depth

Engineering constraint, not a direct property-transaction concern for most buyers

Once complete, the tunnel is expected to cut travel time between Orange Gate and Marine Drive to around five minutes, and to improve connectivity toward the Navi Mumbai International Airport by linking with the Coastal Road and Atal Setu. For anyone with property interests in the Marine Drive Precinct specifically, the relevant question is not whether the tunnel will boost value, but whether the revised southern alignment will run directly beneath or immediately adjacent to a specific building, and whether that building falls within the heritage-protected zone that has already generated one Bombay High Court dispute over redevelopment rights.

FREE
Survey Number Layer

Access Survey Numbers

View on Map

Boundaries and numbers come from published state cadastral records. See all map layers.

For Land Owners & Agents

Looking to sell your land in Maharashtra?

List via WhatsApp
For Land Buyers

Browse all verified lands & plots in Maharashtra

View on Map

Frequently Asked Questions

Source

Official government land and infrastructure records

Official Website

mmrda.maharashtra.gov.in

Coordinate Reference System

EPSG:4326 (WGS 84)

Geometry Type

LineString / MultiLineString

Data Format

Vector (GeoJSON) + Raster Tiles

Last Verified

2026

Status

Active